66b Wharenui Road, Upper Riccarton

12 August 2022
Raft excavation 5

Demolition, earthworks, retaining walls and civil construction 

Our client is constructing a new 82 unit development with a road, carparking and external landscaping. Our scope of works includes:

  • Demolition of existing site buildings and site clearance
  • Installing and maintaining sediment control measures including excavation of a sediment control detention tank
  • Contamination removal
  • Bulk excavation and backfill for units and hard landscaping areas
  • Road construction
  • Timber retaining walls
  • Civil construction - driveways, carparks, footpaths, kerb & channel, line marking and wheel stops 

 

Project Achievements 

  • Maintained compliance with Ecan/ resource consent conditions regarding sediment control requirements. 
  • Due to the scale and large scope of our works we have successfully engaged with a range of subcontractors to allow us to meet contract requirements and stay ahead of the construction programme. In particular our strong relationships with subcontract trucking companies has allowed us to move large volumes of materials in/ out of site to efficiently complete the earthworks portion of the job. 
  • Extensive hard landscaping works including; placement of 4000m2 of concrete for internal road. 

Looking for experienced contractors? 

Contact one of our experienced team today to see how we can help with your next residential or commercial project. 

Back to Articles