Demolition, earth works and civil construction

Our client constructed a 6 unit development with carparking and external landscaping. Our scope included bulk earthworks of around 850 ton of material excavated and removed, and 500 ton of imported material for the following:

  • Demolition of existing house and general site clearance
  • Foundation base course for the units
  • Construction of 150mm thick concrete car park and paths
  • Construction of permeable paved car parking
  • Extensive timber retaining walls
  • Driven timber piles for underground service bridging

Project Achievements

  • Worked closely with geotech consultants and engineers to implement changes to methodology after wet weather impacted retaining wall construction. 